April 1, 2000
Vol.8, No.8
ENVIRONMENTAL REVIEWS COMPLETED
Project reviews completed from February 15 to March 15 are listed below. These projects have been screened through the internal environmental review process for potential impacts on wetlands, threatened and endangered species, and cultural and archaeological resources, etc. Through the review process it was determined that environmental impacts have been kept to a minimum and mitigated as necessary and that the projects do not meet the criteria for significant actions as defined in the environmental review process and may proceed. All of these projects are in compliance with the Endangered Species Protection Act, Natural Areas Preservation Act, Interagency Wetlands Policy Act, and cultural resource statutes.
Horseshoe Lake State Park0001051 - This project involves the installation of ½" telephone wires at the site. The wires will be installed by using a plow blade at a depth of 12". Project was submitted for review on 2-14-00.
North Point Marina
0000788 - New fiber optic cable to
replace existing wire cable is being installed at the site. The cable will
be attached to existing utility poles located along the entrance road and
then will be installed underground using a vibrating plow to the administration
building. From there they will run north and south to feed into the dock
system. Project was submitted for review on 2-8-00.
Beaver Dam State Park
0001045 - Three trenches will be run
to accommodate new water lines and electrical lines at the site. One trench
will run from the entrance to the site residence. The second will run from
the tent camping area to the new pavilion. The third will run from the
front entrance sign to the existing power pole. Project was submitted for
review on 2-9-00.
Hennepin Canal
0001509 - The Sterling Park District
leases IDNR property which houses Oppold Marina. The Park District is proposing
to install an above ground gas tank for the sale of fuel to boats. This
new fuel tank is a replacement for the buried system which was removed
previously. Project was submitted for review on 3-7-00.
Ten Mile Creek SF&WA
0000782 - One element of this work
will involve the digging of a channel through a causeway between two existing
strip mine lakes at the Belle Rive Unit to permit boat access to the south
lake. The channel will be approximately 15' wide and 6' deep and be approximately
50' in length. The second element will consist of the cleaning out of the
drainage ditch that flows into and out of a strip mined lake to allow water
to back up to the dam of a moist soil wetland unit. From here the water
will be seasonally pumped into the wetland unit. Project was submitted
for review on 2-7-00.
Ten Mile Creek SF&WA
0000783 - This project involves the
construction of a small pond in the wash of an agricultural field to control
erosion and provide wildlife habitat. The pond will be less than ½
acre in size and have a maximum depth of 8' at the dam. Project was submitted
for review on 2-7-00.
Ten Mile Creek SF&WA
0000785 - This project involves modifications
to an existing hiking trail in the Goshen Trail Unit. Work will include
a new connecting loop to a access parking lot, some brush removal, weed
mowing and trail signage. Project was submitted for review on 2-7-00
Ten Mile Creek SF&WA
0000786 - This project involves the
construction of moist soil management wetlands in waterways of agricultural
fields of the Belle Rive and Goshen Trail Units. The units will have a
pool area of approximately one acre and impound up to 5' of water. Each
unit will manipulate water levels to produce moist soil plants by the use
of a stop log structure. Project was submitted for review on 2-7-00.
Ten Mile Creek SF&WA
0000784 - This project entails the
construction of one lane gravel boat ramps on various strip mine lakes
at the Eads Unit of the site. A gravel parking area that will handle up
to 6 vehicles with trailers will be provided at each of the ramps. Project
was submitted for review on 2-7-00.
Ten Mile Creek SF&WA
0000780 - This project entails the
construction of shallow water wetlands on former strip mined land using
a rice plow/terrace disk. The levees made to impound the water will be
up to 3' high and will not incorporate drainage structures in their design.
Project was submitted for review on 2-7-00.
Sam Dale State Conservation Area
0000442 - This project will allow
the local water district to install a water main around the entire perimeter
of the site. The line will abut the county roads and be within a 10' wide
corridor. Project was submitted for review on 1-6-00.
Mackinaw River SF&WA
0001046 - This project involves the
reconstruction of the main parking area at the site office and maintenance
area. The reconstruction will be confined to the existing pavement. Project
was submitted for review on 2-9-00.
Jim Edgar Panther Creek SF&WA
0000776, 0000777 - The two projects
involve the construction of a standard pit toilet and a picnic shelter
at the Gurney Pond and Geiss Road Pond day use areas. Projects were submitted
for review on 2-11-00.
Jim Edgar Panther Creek SF&WA
0000773 - This project involves the
construction of an archery range and access trail at the site. The range
will have two shooting lanes with a tower and 4 targets each. A fence will
be installed to secure the back side of the range. Project was submitted
for review on 2-11-00.
Mississippi Palisades State Park
61302 - This project consisted of
the review of a proposed 40 room motel facility with a 100 car parking
lot adjacent to Mississippi Palisades State Park. Project
was submitted for review on 12-22-98
Shabbona Lake State Park
0000571 - This project entails the
construction of a 20' x 20' storage building with the campground area to
store materials and machinery. Project was submitted for review on 1-28-00.
Horseshoe Lake Conservation Area
9903358 - This project entails the
development of 10 new wetland areas by building low levees across swales
in existing agricultural fields. Stop log structures will be used for water
level manipulation and management will be directed toward moist soil plant
production. Project was submitted for review on 11-10-99.
Hidden Springs State Forest
0000568 - This project proposed to
improve the existing fire lane road through an area that periodically floods
by raising the grade by 2'. This will ensure access during wet weather
and ensure adequate water retention for existing breeding areas of reptiles
and amphibians. Project was submitted for review on 1-27-00.
Hidden Springs State Park
0000569 - This project involves the
removal of 3 acres of white/ red pine and the area restored with native
prairie species. This action will combine two larger prairie areas into
on large contiguous field to benefit sensitive grassland birds. Project
was submitted for review on 1-27-00.
Fort Massac
0000787 - This project will provide
for the renovation of the existing boat ramp facility at the site. Included
in the work will be a 2 lane concrete ramp, paved parking and maneuvering
area, standard vault toilet, drinking fountain and hydrant, new security
lighting, new kiosk and concrete sidewalks. Reinforcement of shoreline
embankments and existing eroded areas around the perimeter of the area
will also be included. Project was submitted for review on 2-7-00.
Notice of Significant Action
Carlyle Lake ( Eldon Hazlet State Park)
The Department received 16 comment letters concerning the proposed cabin construction at Eldon Hazlet State Park. The majority of comments addressed the issue of new development within known massasauga habitat or use areas.
Though not an agency sponsored project, the Department has worked diligently to see that the massasauga would be recognized as a major consideration for development interests in and around the Carlyle Lake area. Included in these efforts is the current development of a lake wide management plan. This plan, in cooperation with the Corps of Engineers, will be able to address both the needs of the massasauga and development proposals at the lake over the long term. Critical habitat and use studies concerning the biology of the massasauga are currently underway and critical habitat in addition to Corps land will be acquired as it is identified.
With the ongoing studies in place and the identification of habitat and use areas for the massasauga a primary goal, the Department has decided to proceed with the additional cabin development at Eldon Hazlet with the following constraints in mind:
Mr. Kenneth L. Litchfield, CERP Program
Manager
Illinois Department of Natural Resources
Office of Realty and Environmental
Planning
524 S. Second Street
Springfield, Illinois 62701
Phone: (217) 785-5500
All comments must be received by the
close of business on Tuesday, April 16th, 2000.
Questions and Comments
All questions and comments about the environmental review process or this newsletter should be directed to:
Illinois Department of Natural Resources
Div. of Natural Resource Review &
Coordination
524 S. Second Street,
Springfield, IL 62701
Phone: 217/785-5500
Illinois Department of Natural Resources receives federal
financial assistance and therefore must comply with federal anti-discrimination
laws. In compliance with the Illinois Human Rights Act, The Illinois Constitution,
Title VI of the 1964 Civil Rights Act, Section 504 of the Rehabilitation
Act of 1973 as amended, and the U.S. Constitution, the Illinois Department
of Natural Resources does not discriminate on the basis of race, religion,
color, sex, national origin, age or disability. If you believe you have
been discriminated against in any program, activity or facility please
contact the Equal Employment Opportunity Officer, Department of Natural
Resources, One Natural Resource Way, Springfield, IL 62702-1271, (217) 782-7616,
or the Office of Human Resources, U.S. Fish & Wildlife Service, Washington,
D.C. 20240.
All public meetings conducted by the Department of Natural Resources will be accessible to persons with disabilities in compliance with Executive Order No. 5 and pertinent state and federal laws, upon notification of the anticipated attendance. Handicapped persons planning to attend and needing special accommodations should inform the Department of Natural Resources at least five days prior to the meeting by telephoning or writing the Equal Employment Opportunity Officer, Department of Natural Resources, One Natural Resource Way, Springfield, IL 62702-1271, phone (217) 782-7616.
Department of Natural Resources information is available to the hearing impaired by calling DNR's Telecommunications Device for the Deaf: 217/782-9175. The Ameritech Relay Number is 800/526-0844. Printed by the Authority of the State of Illinois. 362-6/97
| 